Agile Planning and Delivery (Azure LaaS)

Vision and Goal of the Project

The vision of this project is to deliver a scalable and efficient Lab-as-a-Service (LaaS) platform on Azure cloud (AKS), enabling organizations to quickly develop, validate, and optimize Wifi chipset solutions using LaaS. This initiative aims to enhance market share by 15% in the next fiscal year, improve team collaboration by 20%, reduce operational overhead by 25%, and provide a secure and robust foundation for cloud-based lab instrumentation services.

The primary goal is to leverage Agile methodologies to achieve:

  • Timely Delivery: Deploy a Minimum Viable Product (MVP) within 6 (2-week) sprints, completing all story points of high-priority features by the end of Sprint 4.
  • Stakeholder Alignment: Conduct bi-weekly sprint reviews with stakeholders to ensure at least 90% of their Must-Have requirements are delivered by the MVP release.
  • Flexibility: Incorporate up to two minor change requests per sprint (each estimated at 3 story points or fewer) without reducing the planned sprint velocity or extending the sprint duration. Track and document the impact of changes to ensure sprint goals are achieved with at least 95% completion rate for planned tasks.
  • Cost Efficiency: Maintain a project budget of $350,000 ± 10% by stakeholder collaboration for backlog refinement and leveraging accurate estimates and simulations, including Monte Carlo simulations for budget validation.
  • Quality Assurance: Ensure a defect leakage rate below 5% for all delivered features by leveraging automated testing, quality assurance tools, test-driven development (TDD), and cost-effective CI/CD strategies to streamline deployment processes.

Key Constraints for the Lab-as-a-Service (LaaS) Project:

ConstraintDescription
Time Constraints
  • Deliver MVP within 4 sprints (each Sprint duration = 2 weeks).
  • Strict adherence to sprint schedules without extensions.
  • Bi-weekly stakeholder reviews.
Scope Constraints
  • Complete all story points of high-priority features by Sprint 4.
  • Limit change requests to two per sprint (3 story points each).
  • Deliver 90% of Must-Have requirements in the MVP.
Budget Constraints
  • Maintain budget within $350,000 ±10%.
  • Use simulations for cost estimation and validation.
  • Reduce operational overhead by 25%.
Quality Constraints
  • Ensure defect leakage rate below 5%.
  • Mandate automated testing, TDD, and CI/CD pipelines.
  • Achieve QA goals cost-effectively.
Technology Constraints
  • Deliver LaaS platform on Azure Cloud (AKS).
  • Provide secure and robust foundation for cloud-based services.
Stakeholder Engagement Constraints
  • Conduct bi-weekly sprint reviews for alignment.
  • Collaborate on backlog refinement to prioritize effectively.
Team and Process Constraints
  • Adhere to Agile practices with 95% sprint goal completion.
  • Enhance team collaboration by 20%.
Risk Constraints
  • Track and document change impact to ensure goals are met.
  • Address security risks to ensure platform robustness.

* Note: Budget amounts are specified for example purpose only

By focusing on these quantifiable goals, the project aims to establish a future-proof foundation for lab services, adaptable to evolving organizational needs.

Business Case Statement

Traditional lab environments face challenges such as high operational costs, limited scalability, and prolonged setup times, hindering timely product development and market entry. The LaaS platform addresses these inefficiencies by providing a scalable, secure, and cloud-based solution that improves collaboration by 20%, reduces operational overhead by 25%, and increases market share by 15%

By leveraging Agile practices and cloud technologies, this project aligns with organizational goals to streamline development, enhance ROI, and secure a competitive edge in the market.

The Challenge

Delivering a scalable Lab as a Cloud Service on Azure AKS required navigating a dynamic environment with evolving requirements. The key to success was integrating Agile metrics like velocity, cycle time, and story points into our planning, tracking, and monitoring processes to ensure we met our deadlines without compromising quality.

Project Planning Sequence

The following table outlines the phases and activities to guide the planning and execution of the project, ensuring alignment with Agile principles:

PhaseActivitiesDeliverables
Initiation Phase
  • Develop Project Charter.
  • Identify key stakeholders.
  • Approved Project Charter.
  • Stakeholder Register.
Planning Phase
  • Define project scope and perform initial backlog refinement.
  • Identify and document known risks in the risk register.
  • Analyze risks using Agile techniques (e.g., probability and impact matrix).
  • Create mitigation strategies for high-probability, high-impact risks.
  • Create and prioritize Product Backlog with user stories.
  • Plan sprints and releases, incorporating change request policies.
  • Conduct backlog grooming sessions with stakeholders.
  • Initial Product Backlog with prioritized user stories.
  • Risk register with documented risks and mitigation strategies.
  • Sprint and Release Plans.
Execution Phase
  • Conduct iterative sprints with development and testing.
  • Track progress using Agile metrics (velocity, burndown, cycle time).
  • Hold sprint demos and reviews to showcase progress and gather stakeholder feedback.
  • Refine scope and backlog continuously based on sprint outcomes.
  • Incorporate approved change requests (limited to two per sprint).
  • Monitor budget and resource utilization during sprints.
  • Adjust sprint and release plans based on feedback.
  • Conduct sprint retrospectives to identify improvements, risks, and review unresolved issues.
  • Incrementally delivered MVP features.
  • Updated and refined backlog.
  • Capture lessons learnt and action items from retrospectives.
  • Progress Reports for stakeholders.
  • Risk register updated with resolved and new risks.
  • UAT test cases and initial results for critical sprint features.
Closing Phase
  • Deliver final product to stakeholders for review.
  • Perform overall UAT to validate all features meet acceptance criteria.
  • Incorporate UAT feedback and resolve any identified defects or issues.
  • Hold a project demo for stakeholders to review the completed product.
  • Review unresolved risks and incorporate them into a post-project analysis.
  • Conduct final sprint retrospective to capture lessons learned.
  • Document project closure and gather stakeholder feedback.
  • Final Product Delivery.
  • Lessons Learned Report.
  • Stakeholder Feedback Summary.
  • Approved UAT results with sign-offs from stakeholders.

Project Charter: Data-Driven Foundation

The Project Charter , described below, was built on a data-driven foundation. This approach ensured accurate estimates for timeline, scope, and budget while incorporating contingencies. The charter also outlined why certain approaches were selected and others omitted to address risks and uncertainties effectively.

1. Scope Definition in Agile

The project scope was defined iteratively to align with stakeholder needs while maintaining technical feasibility. We employed several Agile methodologies to ensure a flexible and adaptive approach:

MethodActivitiesOutcomeRationale
Stakeholder WorkshopsCollaborated with sponsor and product mgmt. to identify
Must-Have
,
Should-Have
,
Could-Have
, and
Won’t-Have
features using the
Identified and prioritized features for development.Ensured alignment with stakeholder expectations and defined clear priorities.
User Story MappingVisualized the end-to-end user journey to identify key features and prioritize based on value delivery.Mapped the user journey to focus on high-value features first.Streamlined the backlog by focusing on maximum user impact features.
Gap AnalysisIdentified critical gaps like CI/CD pipeline automation and role-based access necessary to achieve the desired state.Highlighted foundational requirements and risks.Ensured critical gaps were addressed early in the project.
Incremental Scope RefinementDecomposed scope into manageable epics and user stories for iterative delivery, enabling continuous feedback and adjustments.Created a flexible and iterative approach to scope definition.Allowed dynamic adjustments based on stakeholder feedback and progress.
Product Backlog GenerationConverted the scope into a prioritized product backlog containing detailed user stories, tasks, and acceptance criteria.Provided clear task breakdown for developers.Streamlined sprint planning with a ready-to-execute backlog.
Sprint Planning and ReviewsIteratively refined scope based on sprint outcomes and stakeholder feedback.Maintained alignment with evolving stakeholder needs.Enabled continuous prioritization and value-driven delivery.

2. Evaluating the Timeline

A combination of methods ensured an accurate and realistic timeline:

  • Historical Data: Past cloud-based projects on Azure provided a benchmark for estimating similar deliverables. Comparable projects took 12 weeks for MVP delivery.
  • Velocity Analysis: Using a team velocity of 30 story points/sprint, the timeline was calculated as 3 sprints to complete a 90-story-point backlog.
  • Three-Point Estimation: Factored in uncertainty with optimistic (10 weeks), most likely (12 weeks), and pessimistic (14 weeks) scenarios, averaging to a timeline of ~12 weeks.

Why Other Approaches Were Not Chosen:Sole reliance on critical path analysis was avoided because it doesn`'`t account for iterative delivery and dynamic backlog refinement, both critical in Agile environments.

Calculating the Budget

The budget was estimated using a bottom-up approach with contingencies:

  • Resource Costs: Developer costs were calculated as $100/hour for a 5-person team working 20 hours/week over 12 weeks, totaling $120,000.
  • Azure Services: Used theAzure Pricing Calculator to estimate infrastructure costs (~$50,000 for compute and storage).
  • Contingency Buffer: Added 20% to account for unforeseen risks, resulting in a total budget of $250,000.

Why Other Approaches Were Not Chosen:Top-down estimation alone was avoided as it often overlooks granular resource costs and task-specific complexities.

Budget Estimation Using 3-Point Estimates

The budget for delivering Lab as a Cloud Service onAzure AKS was calculated using a data-driven approach:

  • Optimistic Estimate (O): $300,000, assuming no delays or major risks.
  • Most Likely Estimate (M): $350,000, based on historical data and typical project complexities.
  • Pessimistic Estimate (P): $400,000, accounting for potential delays or unforeseen challenges.

The final budget was calculated using the 3-point estimation formula:
Expected Budget = (O + 4M + P) / 6

Result: ($300,000 + 4 × $350,000 + $400,000) / 6 = $350,000.

Monte Carlo Simulation for Budget Validation

To enhance the accuracy of the budget estimation, a Monte Carlo Simulation was performed. This simulation evaluates potential budget outcomes by running thousands of random iterations using the 3-point estimate ranges.

Simulation Process

  • Generate random values for budget inputs within the range of theOptimistic andPessimistic estimates.
  • Use the weighted formula (O + 4M + P) / 6 to calculate expected budgets for each iteration.
  • Run the simulation 10,000 times to create a distribution of potential budget outcomes.

Results

The Monte Carlo Simulation provided the following insights:

  • Mean Budget: $350,000.
  • 90% Confidence Interval: $335,000–$370,000.
  • Outliers: Less than 2% of simulations exceeded $400,000.

This analysis confirmed that the estimated budget of $350,000 is realistic, with a high probability of staying within the specified range.

Capacity and Capability Metrics

The project team’s capacity and capability were evaluated based on their roles and skills:

RoleSkillsCapacity (Hours/Week)Velocity (Story Points/Sprint)
Software ArchitectAzure AKS, CI/CD, Kubernetes205
Senior Software EngineerAPI Integration, Cloud Deployment4020
Junior Software EngineerFrontend (React.js), Debugging4010
QA EngineerManual Testing, Selenium405

Total Team Velocity: 40 story points/sprint (2-week sprint).

Reference Register for Team Velocity

To align team velocity with seniority levels, we used the following reference register:

  • Junior Engineers: 5–10 story points/sprint, depending on task complexity.
  • Senior Engineers: 15–20 story points/sprint, including mentorship responsibilities.
  • Architect: 5 story points/sprint, focusing on design and reviews.
  • QA Engineers: 5 story points/sprint, covering testing and automation tasks.

Team Composition, Costs, and RACI

The team structure was carefully planned to balance experience, cost-efficiency, and project complexity. Each role is defined with responsibilities, the RACI model, and skillsets:

The team structure was carefully planned to balance experience, cost-efficiency, and project complexity. Each role is defined with responsibilities, the RACI model, and skillsets:

RoleRACIResponsibilitiesTechnical SkillsNon-Technical SkillsHourly Rate ($)Weekly Cost
Software ArchitectR: Architecture Design
A: System Scalability
C: Cloud Selection
I: Development Team
Designs architecture, ensures scalability, and reviews technical decisions.Azure AKS, Kubernetes, CI/CD pipeline designLeadership, Stakeholder Communication, Problem-solving150$6,000
Senior Software EngineerR: Development
A: Code Quality
C: Junior Engineers
I: Architect
Develops complex modules, implements CI/CD pipelines, mentors juniors.API Integration, Cloud Deployment, Backend Development (Node.js, Python)Collaboration, Mentorship, Analytical Thinking100$4,000
Software EngineerR: Basic Development
A: Code Implementation
C: Senior Engineers
I: Architect
Writes reusable code, debugs issues, and assists in frontend tasks.Frontend Development (React.js), Debugging, Basic Cloud ConceptsTime Management, Learning Agility, Attention to Detail65$2,600
QA EngineerR: Testing
A: Defect Management
C: Development Team
I: Architect
Writes test cases, performs integration testing, ensures product quality.Automation Testing (Selenium), Performance Testing, API TestingDetail Orientation, Critical Thinking, Documentation60$2,400
Technical Manager/LeadR: Oversight
A: Stakeholder Alignment
C: Architect
I: Entire Team
Oversees progress, aligns stakeholders, and resolves conflicts.Agile Methodologies, Budget Management, Project Planning Tools (Jira)Leadership, Communication, Strategic Thinking120$4,800

* Note: All rates and cost are specified for example purpose only

Estimated Weekly Team Cost: $19,800
Weekly Planned Costs (Travel, training etc.): $1000
Total Cost (12 Weeks): $249,600

Monte Carlo Simulation for Budget Validation

To enhance budget accuracy, a Monte Carlo Simulation was performed, evaluating outcomes over 10,000 iterations.

Simulation Insights

  • Mean Budget: $350,000
  • 90% Confidence Interval: $335,000–$370,000
  • Outliers: Less than 2% exceeded $400,000

Combined Budget Summary

The total project cost is summarized below:

  • Team Costs: $249,600
  • Tools & Resources: $59,220
  • Contingency (15%): $46,323

Total Project Cost: $295,923

Risk Assessment and Contingencies

A proactive risk assessment ensured contingencies for potential challenges:

  • Key Risks: Delays in feature delivery, infrastructure scaling issues, and evolving requirements.
  • Mitigation Strategies: Conducted regular sprint reviews, integrated automated testing early, and maintained flexible backlog prioritization.
  • Contingency Planning: Allocated buffer resources and time for high-risk tasks.

Realistic and Adaptive Charter

Incorporating these data-driven evaluations and contingencies ensured theProject Charter was both realistic and adaptable, laying the groundwork for a successful Agile execution.

Gap Analysis

A Gap Analysis was conducted to identify areas needing improvement between current capabilities and project objectives:

  • Current State: Manual lab setup processes causing delays and inconsistencies.
  • Desired State: Automated lab environments deployable within minutes via Azure AKS.
  • Key Gaps: Lack of CI/CD pipelines, limited monitoring, and resource over-provisioning.

The analysis informed the backlog prioritization and roadmap development, focusing on closing these gaps in early sprints.

Roadmap Building

A roadmap was created to outline milestones and delivery timelines:

  • Sprint 1: Deploy core lab services and enable basic monitoring.
  • Sprint 2: Implement role-based access and CI/CD pipelines.
  • Sprint 3: Finalize MVP testing, performance optimization, and deployment.

The roadmap ensured alignment between team capacity and stakeholder expectations, adapting as needed based on sprint reviews.

Execution: Driving Progress with Agile Metrics

During execution, these metrics served as our guide:

  • Velocity Tracking: Used velocity charts to monitor completed story points, ensuring we stayed on pace for roadmap milestones.
  • Sprint Burndown Chart: Provided daily insights into remaining work and potential scope creep.
  • Cumulative Flow Diagram (CFD): Visualized workflow trends and ensured tasks flowed efficiently across statuses.

Monitoring: Insights Through Metrics

Continuous monitoring ensured transparency and alignment with stakeholder expectations:

  • Cycle Time: Reduced average cycle time by 20%, improving task delivery speed.
  • Burnup Chart: Tracked cumulative progress, ensuring focus on sprint and epic goals.
  • Workload Distribution: Ensured balanced allocation using tools like Tempo Planner to prevent burnout.

The Outcome

By leveraging Agile metrics effectively, we delivered a high-qualityLab as a Cloud Service application on time and within scope. Key achievements included:

  • Improved velocity by 15% over the course of the project.
  • Reduced average cycle time by 20%, enabling faster task completion.
  • Maintained a defect leakage rate below 5%, ensuring stakeholder confidence.